
byCollegedunia Team Content Curator
Question: A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, (4/7) of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours?
(A) 80
(B) 81
(C) 82
(D) 83
(E) 84
Correct Answer: B
Solution and Explanation:
Approach Solution 1:
This question has only one approach
The given condition in a contract states that it is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, (4/7) of the work is completed. Accordingly, it is to find the number of additional men who may be employed so that the work may be completed in time, with each man now working 9 hours. Let the total man-hours may be assumed to be x.
Based on the given situation, after 33 days, 4/7th of the work is said to be completed. Accordingly, if it is assumed that each worker works 1unit of work in one hour, then in 33 days, 117*8*33 hours of work are completed.
By assuming that the total man hours as x, the man-hours completed after 33 days implicating 4/7th of the work can be equated as follows:
\(\rightarrow\frac{4x}{7}=117*8*33\)
\(\rightarrow x=117*7*8*33\)
\(\rightarrow x=117*7*33*2 \) man hours
In order to complete the given contract of work in time, it is important to employ an additional number of men as given in the condition. Accordingly, it evaluates that with an additional number of men each worker to complete the work in time would need to work 9 hours. This implies that the additional man hours left for the completion of the task is as follows:
= 117∗7∗33∗2−117∗8∗33
= 117∗33∗(14−8)
= 117∗33∗6 man hours
Hence, 117∗33∗6 man hours is left for the entire contract to be completed.
Considering that the contract is for 46 days and 33 days of work is already complete, the number of days left to complete the contract is 13days.
With this, let the total number of men required for work of completing the contract be m. To find the number of additional men required, the following can be resolved:
m∗9∗13=117∗33∗6
\(\rightarrow m=\frac{117*33*6}{9*13}=198\)
Accordingly, the total number of men to be working for the contract is 198. However, the number of additional men to be working can be subtracted from the total number of men who are supposed to work. This implies 198 with the number of men who have completed 4/7th of the task which is 117. This implies-
198 - 117 = 81.
Thus, the additional number of men required for the contract to be completed with workers at 9 hours of work for the next 13 days is 81.
“A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day.”- is a topic of the GMAT Quantitative reasoning section of GMAT. To solve GMAT Problem Solving questions a student must have knowledge about a good amount of qualitative skills. GMAT Quant practice papers improve the mathematical knowledge of the candidates as it represents multiple sorts of quantitative problems.
Suggested GMAT Problem Solving Questions
- A machine puts c caps on bottles in m minutes. How many hours will it GMAT Problem Solving
- What is the least common multiple of 15, 18, and 24? GMAT Problem Solving
- The Price of Darjeeling Tea (in rupees per kilogram) is 100+0.10n GMAT Problem Solving
- A Migraine Typically Afflicts One Side of the Head, Lasts for Hours GMAT Sentence Correction
- A 5-meter-long wire is cut into two pieces. If the longer piece GMAT Problem Solving
- The average weight of 15 items is 8 kg. The least average GMAT Problem Solving
- In a class of 78 students 41 are taking French, 22 are taking German GMAT Problem Solving
- If |x| > 3, which if the following must be true? GMAT Problem Solving
- 100 students appeared for two examinations. 60 passed the first GMAT Problem Solving
- An integer between 1 and 300, inclusive, is chosen at random GMAT Problem Solving
- In How Many Ways Can 6 Chocolates Be Distributed Among 3 Children GMAT Problem Solving
- A Man Can Row 50 Km Upstream And 72 Km Downstream In 9 Hours GMAT Problem Solving
- A Sum Of Money Doubles Itself In 7 Years. In How Many Years It Becomes Four Fold GMAT Problem Solving
- On Selling A Pen At 5% Loss And A Book At 15% Gain, Karim Gains Rs. 7 GMAT Problem Solving
- If Two Typists Can Type Two Pages in Two Minutes, How Many GMAT Problem Solving
- An Empty Pool being Filled with Water at a Constant Rate takes 8 hours GMAT Problem Solving
- For Every Positive Even Integer n, the Function h(n) is Defined to be GMAT Problem Solving
- The formula F = 9/5 * C + 32 gives the relationship between the temperature GMAT Problem Solving
- A Takes 5 More Days Than B To Do A Certain Job And 9 Days More Than C GMAT Problem Solving
- A Watch Which Gains 5 Seconds In 3 Minutes Was Set Right At 7 A.M. GMAT Problem Solving
- Of The 800 Employees Of Company X, 70 Percent Have Been With The Company GMAT Problem Solving
- To 100 Litres Of Milk, 10 Litres Of Water Is Added And Then 20 Litres GMAT Problem Solving
- Walking at 3/4 of his normal speed, Mike is 16 minutes late GMAT Problem Solving
- There are 12 yes or no questions. How many ways can these be answered? GMAT Problem Solving
- There are 7 Red and 5 Blue Marbles in a Jar GMAT Problem Solving
- A Basket Contains 3 White and 5 Blue Balls GMAT Problem Solving
- Working together, John and Jack can type 20 pages in one hour GMAT Problem Solving
- Is x^2 *x^5*z>0? GMAT Problem Solving
- The average (arithmetic mean) of four distinct positive integers is 10 GMAT Problem Solving
- How many roots does the equation √x2+1+√x2+2=2 have? GMAT Problem Solving
- A Box Contains 10 Tablets of Medicine A and 15 Tablets of Medicine B GMAT Problem Solving
- If x=√10+3√9+4√8+5√7+6√6+7√5+8√4+9√3+10√2, then which of the following must be true? GMAT Problem Solving
- What is the last digit of (3)^(3)^3? GMAT Problem Solving
- It takes Jack 2 more hours than Tom to type 20 pages GMAT Problem Solving
- The angles in a triangle are x, 3x, 5x degrees GMAT Problem Solving
- If among 5 children, there are 2 siblings; in how many ways can the children be seated GMAT Problem Solving
- Among 200 People, 56% like Strawberry Jam, 44% like Apple Jam, and 40% like Raspberry Jam GMAT Problem Solving
- If 4 Women and 6 Men Work in the Accounting Department GMAT Problem Solving
- If 2^98=256L+N, where L and N are integers and 0≤N≤4, what is the value of N? GMAT Problem Solving
- A draining pipe can empty a pool in 4 hours. GMAT Problem Solving
- If equation |x| + |y| = 5 encloses a certain region on the graph, what is the area of that region? GMAT Problem Solving
- Kate and David each have $10. GMAT Problem Solving
- How many five digit numbers can be formed using the digits 0, 1, 2, 3, 4, and 5 which are divisible by 3, without repeating the digits? GMAT Problem Solving
- Which of the following lines are parallel to line x = 4 – 2y? GMAT Problem Solving
- John has 12 clients and he wants to use color coding to identify each client GMAT Problem Solving
- Which of the following expressions has the greatest values? GMAT Problem Solving
- If @ x=x^2/2x^2-2 , What is the Units Digit of @ (@4)? GMAT Problem Solving
- What is the product of all possible solutions of the equation |x+2|- 5|x+2| = -6? GMAT Problem Solving
- If 69% of k is 23, approximately how much is 23% of k? GMAT Problem Solving
- Metropolis Corporation has 4 Shareholders GMAT Problem Solving
Comments